Skip to content

Heat Pump Electrical Calculator

Calculate cable size, MCB, and supply requirements for air source heat pumps

Reference Info & Formulas
Quick Guide

5-8kW: Single phase usually OK

10-12kW: Check supply capacity

16kW+: Three phase recommended

Type C MCB for compressor starting current

Key Points

Isolator within sight of outdoor unit

Type A RCD minimum

Check DNO supply adequacy

MCS installer certification required

Heat Pump Details
Select the heat pump rating
Cable Route
Cable run to outdoor unit
Existing Loads
Do you have an immersion heater?

Data: BS 7671:2018+A2:2022, MCS Standards

For guidance only. The responsibility for any electrical installation lies with the qualified person carrying out the work. Always verify calculations independently and apply professional judgement.

How This Calculator Works

Heat pump circuit design accounts for continuous compressor loads, high starting currents, and coordination with the existing supply capacity.

The calculator sizes the circuit based on the heat pump's maximum operating current from the manufacturer's data sheet, not the nominal kW rating. Compressor motors are treated as continuous loads with significant inrush current on start-up, requiring careful MCB type selection and cable sizing.

I = P / (V × PF) [single-phase]
I
= Full load current (A)
P
= Heat pump rated input power (W)
V
= Supply voltage — 230V single-phase
PF
= Power factor — typically 0.85-0.95 for heat pump compressors

For three-phase: I = P / (√3 × V × PF), where V = 400V

After determining the full load current, the calculator selects a cable size from Table 4D5 (T&E) or Table 4D4A (SWA for outdoor runs), applies correction factors for ambient temperature, grouping, and thermal insulation, then verifies voltage drop is within the 5% limit. A Type C MCB is selected to handle compressor inrush without nuisance tripping.

Quick Reference — ASHP Circuit Sizing

Typical air source heat pump circuit requirements

BS 7671 Table 4D5, manufacturer data
Heat Pump RatingSupplyCurrent DrawCable Size (Method C)MCB
5kWSingle-phase22A4mm² T&E (37A)25A Type C
8kWSingle-phase35A6mm² T&E (47A)40A Type C
12kWSingle-phase52A10mm² T&E (64A)63A Type C
12kWThree-phase17A per phase2.5mm² (24A)20A Type C
16kWThree-phase23A per phase4mm² (32A)25A Type C
20kWThree-phase29A per phase4mm² (32A)32A Type C

Values assume Method C (clipped direct), 30°C ambient, PF 0.85, no grouping or insulation derating. Always verify against the specific manufacturer's maximum current rating.

Quick Reference — Supply Adequacy

Typical domestic maximum demand with heat pump

IET Guidance Note 1, Appendix H
LoadDemand (A)With Diversity
Existing domestic load (diversified)40-60A
8kW ASHP (single-phase)35ANo diversity applied
12kW ASHP (single-phase)52ANo diversity applied
7kW EV charger32ANo diversity applied
Immersion heater (3kW backup)13AMay apply diversity with ASHP

Heat pumps and EV chargers are continuous loads — no diversity reduction. A maximum demand calculation should be performed before installation to confirm supply adequacy.

Practical Notes

Supply Overload Risk

Adding a heat pump to a property with an existing EV charger, electric shower, or high base load can exceed the 100A main fuse rating. An overloaded supply fuse may not trip immediately but will degrade over time and eventually fail — potentially causing a supply outage in cold weather when the heat pump is most needed. Always perform a maximum demand assessment and consider DNO notification or a supply upgrade if the total demand approaches 80% of the service fuse rating.

Type C MCB — Not Type B

Heat pump compressors draw 4-6 times FLC on start-up. A Type B MCB (3-5× trip) will likely nuisance-trip on every compressor start cycle, particularly in cold weather when the compressor works hardest. Type C (5-10× trip) is the standard specification. Some larger units may require Type D — always check the manufacturer's installation data sheet.

DNO Notification May Be Required

Under the Electricity Safety, Quality and Continuity Regulations (ESQCR) and G98/G99, you may need to notify the Distribution Network Operator (DNO) before connecting a heat pump, especially if the total installation demand exceeds certain thresholds or if a supply upgrade is needed. For single-phase connections above approximately 13.8kW total new load, or any three-phase connection, notification is typically required. Check with the local DNO.

Frequently Asked Questions

SparkyHub is a free resource built by Taro Schenker — I build websites for trade businesses too.

Related Calculators

Built by Taro Schenker · Need a website for your trade business? Get in touch