Skip to content

DNO Application Checker

Check if your installation needs a G98 notification or G99 application

Reference Info & Formulas
G98 vs G99

G98: Up to 16A/phase. Fit and notify — no wait.

G99: Above 16A/phase. Full application — await DNO approval.

Single phase: 3.68kW limit for G98

Three phase: 11.04kW limit for G98

Key Points

MCS certification required for installer

Existing generation capacity counts toward limit

CT metering may be needed above 30kW

Installation Details
What are you installing?
Existing Generation
Any existing generation already connected?

Data: ENA EREC G98 & G99

For guidance only. The responsibility for any electrical installation lies with the qualified person carrying out the work. Always verify calculations independently and apply professional judgement.

How This Checker Works

This tool determines whether a generation installation requires a G98 notification or G99 application based on the system's capacity, phase configuration, and technology type.

The key threshold is 16A per phase, which equates to 3.68kW on a single-phase 230V supply (16 × 230 = 3,680W). Installations at or below this limit follow the simpler G98 notification route. Anything above — or any three-phase installation regardless of size — requires a full G99 application with DNO approval before commissioning.

Where multiple generation sources are present (e.g. solar PV plus battery storage), the total inverter capacity is aggregated. A 3kW solar inverter combined with a 3kW battery inverter totals 6kW, which exceeds the G98 threshold and requires a G99 application even though each inverter individually falls below the limit.

Quick Reference — G98 vs G99

ENA Engineering Recommendation comparison

ENA EREC G98 Issue 5, G99 Issue 7
G98 (Notification)G99 (Application)
Capacity limit≤16A per phase (≤3.68kW)>16A per phase (>3.68kW)
PhaseSingle phase onlySingle or three phase
ProcessNotify DNO, no approval neededApply and await written approval
Response timeNone — install after notificationUp to 45 working days
Commissioning formG98 notification formG99 commissioning confirmation
CT meteringNot requiredRequired above 30kW (varies by DNO)
Export limitingNot typically requiredMay be required by DNO

Thresholds are based on total inverter capacity across all generation sources at the premises.

Quick Reference — Common Installation Scenarios

Typical generation installations and their DNO requirements

ENA EREC G98, G99
InstallationTypical CapacityRouteNotes
Domestic solar PV3-4kWG98 or G99G98 if ≤3.68kW; G99 if above
Solar PV + battery3kW + 3kW = 6kWG99Aggregate capacity exceeds 3.68kW
Commercial solar PV10-50kWG99CT metering likely above 30kW
Battery storage only3.6kWG98If inverter capacity ≤3.68kW
Wind turbine1-6kWG98 or G99Depends on rated output
Standby generatorVariesG99If parallel operation with grid

Standby generators operating in island mode (not exporting) may not require DNO notification, but always confirm with your DNO.

Practical Notes

Never Energise Before G99 Approval

Connecting a generation system to the grid without G99 approval is a serious breach of the Electricity Safety, Quality and Continuity Regulations (ESQCR). The DNO has the legal right to disconnect the supply without notice. This also invalidates any feed-in tariff or Smart Export Guarantee (SEG) payments and may void the installer's MCS certification.

Aggregate All Generation Sources

The G98/G99 threshold applies to the total generation capacity at the premises, not per device. If a property already has a 2kW solar array and you add a 2.5kW battery inverter, the combined 4.5kW exceeds the 3.68kW G98 limit. The entire installation then requires a G99 application covering all generation sources.

Submit G99 Applications Early

The 45 working day response window can delay project completion significantly. Submit the G99 application as soon as the system design is finalised — ideally before ordering equipment. Many DNOs offer online portals for applications, making it straightforward to submit early and track progress.

DNO-Specific Requirements Vary

Each DNO may have additional requirements beyond the ENA recommendations. Some require export limiting on all G99 installations, others set CT metering thresholds at 16kW rather than 30kW. Always check the specific requirements of the local DNO (UKPN, SSEN, WPD/National Grid, SP Energy Networks, etc.) before finalising the design.

Frequently Asked Questions

SparkyHub is a free resource built by Taro Schenker — I build websites for trade businesses too.

Related Calculators

Built by Taro Schenker · Need a website for your trade business? Get in touch